Flowable Fill Project

Cellular Concrete Grout Production Services 2023 Flowable Fill Project

Read about our most recent flowable fill project completed in 2023 that began with a 5:00AM equipment set up time on location.

Pipe Abandonment Project

Total LNFT of Pipes: 16,672
Total CUYD of Cellular Concrete: 12,548
Cellular Concrete Low Density: AVG. 40 PCF
Abandonment Project Completed in: 42 Days
Daily Placement of Cellular Concrete: 350 CUYD